On this installation WarmFloors was asked to supply and install water underfloor heating to the new extension and utility room.
During the technical site survey we discovered the builder had already installed an insulated concrete pad leaving just enough room for the underfloor heating pipes and 50mm flowing screed.
Using 50mm low profile pipe former trays we were able to install the pipe successfully and the screed.
On this project we also connected the manifold to the boiler and wired in the controls a few days later.